Saturday, 15 October 2011

15 October 2011

Thirteenth meeting on 15 October 2011 2pm - 6pm
Venue: Ang Mo Kio National Library


  • Development of the system design - we come out with a few design of the system and we will come out with a standard main frame.
  • Analyzing the program requirement - implementing the most basic requirement of the system.

Saturday, 8 October 2011

8 October 2011

Twelfth meeting on 8 October 2011 2pm - 6pm
Venue: Ang Mo Kio National Library

Discuss on the outstanding report:


  1. Gannt chart to be completed (activity, timeline)
  2. Implementing the prototype from the previous meeting with our beloved assessor.
  3. Discussion of the development tools.

Saturday, 1 October 2011

1 October 2011

Eleventh meeting on 1 October 2011 8.00am - 10am


  • Run through the power-point slide before the lecture. 


  • Touching up of the User Manual, Technique Manual and the Application flowchart.

                                                                                                                                      


1 October 2011 10am - 11am

Lecture on what is expected for the upcoming presentation.


                                                                                                                                      


1 October 2011 12pm - 2pm

Discuss and make final edition of the Application flowchart.
After Application flowchart is completed, we finalize the Prototype power-point adding the screen shot of the Application flowchart.



                                                                                                                                      



1 October 2011 2pm - 2.15pm

First meeting with our beloved assessor Mr. Tan Kheng Teck.

First Prototype presentation on how our final product would look like, and how are we going to implement our product.

Mr. Tan Kheng Teck asked if there are any security aspects for our product, as our product is a tutorial tool for learning C++ programming language, hence our focus would be concentrating on how to do error checking when learners have errors in their program.

Sunday, 25 September 2011

17 September 2011

Tenth meeting on 17 September 2011 11.30am - 12.30pm

Forth meeting with our beloved supervisor Mr. Premarajan.

Discuss on what should we prepare for our next meeting for presentation.

1. PowerPoint presentation with a few slides for our initial presentation.

2. Prototype for our initial product, which include some basic functionality. It is the overview of our product.

3. Technical manual, which include all the technical specification of the software.

4. User manual, to guide the user on how to use our software.

15 September 2011

Ninth meeting on 15 September 2011 1pm - 2pm

1. Discuss on what is needed in the technical manual

  • We discuss about the basic functionality needed in our software, hence we could come out with the technical manual from there.
  • A prototype is needed to come out with the technical manual. 

Sunday, 18 September 2011

10 September 2011

Eigth meeting on 10 September 2011 11.30am - 12.15pm

Third meeting with our beloved supervisor Mr. Premarajan.


1. Discuss on our functionality
  • We were not firm on our functionality yet, because we couldn't decide what could be done and what not.
  • Mr. Premarajan felt we should firm up on the functionality before we start on anything else.

Saturday, 10 September 2011

03 September 2011

Seventh meeting on 03 September 2011, 10.00am - 2.00pm

1. Meet in Nanyang Polytechnic to discuss and solve the comments given by Mr. Premarajan.

2. Added in new sections in our proposal:
  • Development Tools
  • Business Case
  • Project Schedule
  • Blog name